If you're buying a home near Nathrop and plan to work from it, the internet date to watch this winter is Dec. 31, 2026. That's the deadline for both federally funded fiber projects that reach into this part of Chaffee County. By publish day it's about six weeks away. One of the two providers is in Chapter 11 bankruptcy. The other has said its last mile has been slowed by federal funding delays.
For a buyer, that changes what "fiber coming" means on a listing or a coverage map. A grant award is a promise tied to one provider and one deadline. Under the funding rules, the same award that creates the promise also keeps those addresses out of other programs while it's open.
Two grants, one deadline
Both projects are paid for through Colorado's share of the federal Capital Projects Fund. The Colorado Broadband Office keeps the award list public.
| Visionary Broadband | Maverix Broadband | |
|---|---|---|
| Award name | VCN Buena Vista FTTX | Chaffee + Saguache Counties FTTH |
| Award amount | $5,190,064 | $12,832,911 |
| Locations | 1,307 | 1,661 |
| Area described | North of Buena Vista, west of town, south to Nathrop | Southern end of Chaffee County, plus Saguache County |
| Deadline | End of 2026 for full funding | Project end date of Dec. 31, 2026 |
| Latest public update | Construction began April 2025; CEO said in January 2026 the last mile was slowed by BEAD delays | State froze payments in September 2026 |
The Maverix project started with a 2023 county Invitation to Negotiate, in which the county put Maverix forward for "the southern end of the county." According to Ark Valley Voice, county commissioners chose not to put county money into these projects. Their support letters carried no matching funds.
The rest of the story comes from 2026. The Colorado Sun reported that Maverix had been in receivership since the start of the year and filed for Chapter 11 on Aug. 31. In September, the Colorado Broadband Office froze payments, ended the company's active grants, canceled its $103 million award under the federal BEAD program, and referred the case to the Colorado Bureau of Investigation. The state laid out its findings in its own announcement. Maverix cofounder David Lindauer told the Sun the company disputes the findings "in their entirety" and expects the state's conclusions to change once it reviews the records.
Why a funded address can end up waiting longer
The hidden cost is in the program rules. Once a location has public money assigned to bring it service, other programs treat it as covered. The Colorado Sun explained that the Chaffee and Saguache locations in the Maverix contract were left out of earlier BEAD funding because counting them again would have been "double dipping."
So the BEAD round that handed out $420.6 million across Colorado passed over those addresses. Each one already had a grant on paper. The state now says those locations will go back out to bid through BEAD. Alison Terry, the Colorado Broadband Office's interim executive director, told the Sun that any locations still unserved "can go back on our state map." The state hasn't said yet who will win them or when.
Elsewhere in Colorado, a stalled build has left visible marks. The Colorado Sun described Livermore in Larimer County, where a different Maverix contract left miles of buried conduit with no fiber in it and conduit ends sticking out of the ground. A resident there told the paper the state would most likely have to start over. For a buyer, the takeaway is practical. A property inside a stalled grant area could wait longer for fiber than one no program had ever claimed, because the stalled grant first has to be cleared before anyone else can be funded to build there.
The build that does run to Nathrop
The Visionary project ends in Nathrop. Visionary bought the local provider Aristata Communications in February 2024 and moved Aristata accounts onto the Visionary name in April 2025. Ark Valley Voice reported that the change brought more than 4,000 customers in Chaffee and Custer counties under Visionary, with a service area that includes Nathrop, Johnson Village and Chalk Creek.
Visionary's April 2025 announcement described the fiber build as nearly 15 miles long, running from north of Buena Vista, west of town and south to Nathrop, with construction "throughout 2025." Its earlier grant announcement named Game Trail and Trails West on the edge of Buena Vista. At an April 2025 county commissioners meeting, covered by the Chaffee County Times, Visionary's Brian Shepherd said the fiber runs "from Nathrop … all the way up along the west side of 285." He said about 90 percent of it sits on Sangre de Cristo Electric Association poles.
The route matters for buyers. Where a property sits relative to US-285, and whether its power comes on Sangre de Cristo poles, are questions to settle early on any Nathrop listing.
The schedule has moved since then. In a January 2026 interview with Ark Valley Voice, Visionary CEO Brian Worthen called the Nathrop-to-Buena Vista fiber project a priority. He said it "remains at the mercy of evolving Federal to State handoff" and that the last mile was being slowed by the nationwide BEAD stall.
South of Nathrop, the plans are still forecasts. At the same April 2025 meeting, Shepherd said Visionary had preliminary BEAD selection worth about $3.7 million, and that its Round 2 application would fill gaps "from Nathrop south to Mesa Antero." Separately, Visionary said it expected at least part of another state grant to cover the Chalk Creek and Mesa Antero areas, using fiber and fixed wireless where fiber can't go, over about two years.
Why wireless and satellite still matter here
For now, many homes in rural Chaffee County will get service from a tower or a satellite. Worthen's January comments explain why providers are moving toward fiber. He said tower rent in one municipality jumped from $450 to more than $1,500 a month, and that fixed wireless hardware usually needs replacing every five to seven years. For the most remote and costly spots, he sees low-earth-orbit satellite services such as Starlink or Amazon's Project Kuiper filling the gaps.
Statewide, that shift is already built into federal funding. The Colorado Sun reported that Amazon's satellite service was chosen to serve 44 percent of Colorado's roughly 96,000 BEAD-eligible locations. In the Livermore story, the resident put it more simply: "Now everybody's got Starlink."
The same Ark Valley Voice piece also warned that coverage maps "often overstate speeds" and miss pockets of poor reliability in valley terrain. It noted that rural installs can take weeks longer than in cities. In a canyon like Chalk Creek, a clear view of the sky or a line of sight to a tower depends on the specific lot.
What to confirm before you write an offer
If internet decides whether a Nathrop property works for you, settle these during the window you set aside for due diligence:
- Order-ready service at the exact address. Ask each provider whether it can install at that address now, what the speeds are, and how long installation takes. A coverage map or a "fiber in the area" note won't tell you that.
- The seller's current setup. Find out who provides service today, what equipment is on site, and whether it stays with the house. A recent bill shows what the home actually gets.
- Where the home sits on the grant map. The Colorado Broadband Office lists awards by provider. If an address falls inside an open grant, the timeline depends on that provider meeting its deadline.
- A backup plan that fits the site. For satellite, check the sky view from the roof or yard. For fixed wireless, ask the provider whether the lot has line of sight to a tower.
- Your work schedule against the install date. If you start working from the house on a set date, compare it with the provider's quoted install timeline.
These steps add to the land checks covered in our guide to buying acreage near Nathrop. Our utilities and services page collects local provider contacts. Buyers shopping from the Front Range can fit internet checks into the remote-purchase process described in buying in Buena Vista from afar.
FAQ
Does Dec. 31, 2026 mean fiber will reach every Nathrop home by New Year's? No. It's the funding deadline for the Capital Projects Fund awards, not a promise of service at any particular address. Visionary has said it must finish by the end of 2026 to receive full funding.
Are Nathrop addresses part of the Maverix project? The county described the Maverix project as covering the southern end of Chaffee County. The Colorado Broadband Office is the place to check whether a specific address falls inside a funded area.
What happens to locations from the canceled Maverix awards? The state has told the Colorado Sun it plans to put them back out to bid through BEAD.
Internet service at a Nathrop property is something to check during a purchase, just like the well or the road. I'm happy to help you put the provider questions on your due diligence list and get answers before your deadlines. Contact Mary Kale to talk through the properties you're considering near Nathrop.